Jul 25
2008
|
|
We have working lights and also working audio at the Carroll Street house. We had the electrical work finish up the details on the lighting. We also have working audio in the kitchen. The kitchen speakers were wired in and the A-Bus audio system was connected up allowing us to plugin an MP3 player to one of the wall inputs to play music in the house while we are working. Its very cool and sounds great! Work has also started on finishing the wiring for all the network and video cabling runs in the house and at the main distribution panel in the mud room. This work should be finished next week, allowing us to run some computer networking tests.
This weekend the garage should be sided as we passed inspections on the framing and the garage electrical work yesterday. Once that is done, we'll be getting a garage door installed and start in on pouring a new driveway.
Tile work has also begun in the bathrooms. We passed inspection on the tile lathe and we will post a picture or two of the tile once its all finished.