Jun 16
2008
|
Progress updates at 395 Carroll StPosted by steve in progress, house projects |
The new garage foundation was poured today which means we should be standing up 2 of the outer walls tomorrow. We are planning to finish up the outer walls of the garage this week and start working on the garage roof this weekend (assuming the walls are completed during the week!).
Inside the house, the framing odds and ends have been finished up in anticipation of HVAC work and electrical work

The general demolition on the inside of the house was completed over the weekend along with clean up of the overgrown brush around the house itself. In keeping with the green philosophy for Phase 2 Homes, we are recycling all of the tree and bush material and reusing it in the landscaping of the house. We