Getting Closer at Carroll StPosted by steve in progress, house projects |
We've been working extra hours to try to get back on schedule at our house on Carroll Street this week. Lots of progress has been made this past week. As of today (Saturday 6/23) we have our trim work done on all the door casing and the window casing on the inside of the house as well as the base boards throughout the house. Painting has started on the trim work inside the house and will
We just wanted to give you a quick sample of the finished floor color. Yesterday they were able to get the floor sanding finished and the stain color applied to the floor. It came out even better than we had anticipated! The floor needs some time to dry before work can continue inside. Kitchen cabinet work should continue offsite while the floor is drying.
The window casing on the inside of the house at Carroll St was finished up and really looks great. We were able to recreate a look similar to that of the original window casing while dressing them up more than the original using our own custom design. Once the painting on the inside is completed they will look fantastic. We are really pleased with how well the work on these came out.
ekend in both the front and back yards. The new sod and sprinkler system makes a huge difference in the outside appearance of the house. Things look really clean. If you get a chance, take a drive by and see what a difference the new lawn makes. We also installed some lighting outside along the walk to the front porch and beneath the big tree in the front yard.
We now have a real roof and gutters on the new garage at the Carroll Street house. It really makes the garage look more finished. We are scheduled to have the framing inspected on the garage tomorrow and if it passes, we move on to siding, electrical and painting.
lacing the front door, trim work, painting, lighting and landscaping are still to be done to complete the front, but we've attached a picture so that you can see the style of the windows.